AI Superpowers Unlocked · Superpower #10

Critical path: start the slow job first

Find the slowest job, start it first, do everything else while it runs.

Critical path is a classic project-management skill, and it speeds up any process, not just AI work. List every task, how long each one takes and what it has to wait for. The longest chain of tasks that wait on each other is the critical path, and it decides the earliest you can possibly finish.

Then I show it on something real: making these videos. The same seven tasks take 26 minutes one after another and 16 minutes when the slow Kling clip is submitted first and everything else is built while it renders. The task times are simplified for the example; Kling clips really do queue for roughly 4 to 10 minutes.

Try it yourself

  1. List every task, how long it takes, and what it has to wait for.
  2. Find the longest chain of tasks that wait on each other: that’s the critical path.
  3. Start the slowest job first and do everything else while it runs.

Find the critical path

Seven tasks that make one video, with how long each takes and what it waits for. The times are simplified for the example. Toggle between doing them one after another and starting the slow job first.

One after another: 26 minutes. Start the slow job first: 16 minutes.

02468101214161820222426Script3Keyframes2Kling clip8Narration3Graphics5Captions2Final edit3Finish 16 min
Critical path5 min slack26 → 16 min (10 min saved)

The critical path is Script → Keyframes → Kling clip → Final edit: 16 minutes. Narration, Graphics and Captions each have 5 minutes of slack, so they can run while the clip renders without moving the finish.

Chapters

  1. 0:00Superpower: Critical path
  2. 0:15What critical path is
  3. 0:22Step 1: list the tasks
  4. 0:30Step 2: find the longest chain
  5. 0:40Slack (float)
  6. 0:46Two ways to finish sooner
  7. 0:55Where it comes from (CPM and PERT)
  8. 1:05Making a video, one task after another
  9. 1:20The slow job: the Kling queue
  10. 1:30Slow job first: 26 minutes becomes 16
  11. 1:40The same trick, all day
  12. 1:56Three steps
  13. 2:04Superpower unlocked

Sources

All superpowers →

Narration is an AI voice (a clone of my own for the lunch footage), and the animation was made with AI tools.

The robot animation is made with Kling. Try Kling with my referral link. It’s a referral link, so signing up through it may earn me credits.

The narration is made with ElevenLabs. Try ElevenLabs with my referral link. It’s an affiliate link, so signing up through it may earn me a commission.